JANET Lightpath Infrastructure Upgrade

 

More information about the upgrade can be found by looking at the Service Evolution document.

 

Project Timetable

Milestone Deadline Status
Core Equipment Delivery 10 December 2008
COMPLETE
Core Equipment Installation 19 January 2009
COMPLETE
Core Equipment Configuration 31 January 2009
COMPLETE
Regional Equipment Delivery 13 February 2009
COMPLETE
Regional Equipment Installation 20 February 2009
COMPLETE
Regioanl Equipment Configuration 27 February 2009
COMPLETE
Lightpath Migration 30 March 2009
COMPLETE
Decomission SDH equipment 30 June 2009  
Project Completion 28 August 2009