Service Desk 0300 300 2212

Supply & Support of Routing & Switching Equipment

Procurement of routing and switching equipment plus associated support services is a core part of JANET(UK)’s business.  JANET(UK) wishes to establish a multi-supplier framework agreement to enable JANET(UK) and other JANET connected organisations to purchase routing and switching equipment plus any required support services.

 

The NEUPC has an existing national framework for Networking Equipment and Consultancy for Convergent Solutions. The framework runs until 31st July 2011 with the option of possible extensions until 31st July 2013. JANET(UK) and the NEUPC have been working together to develop a PQQ with a view to having a joint agreement from 1st August 2012 based on the outcome of this procurement.

Further information can be found in the Prequalification Questionnaire (PQQ) which is available electronically as a word file and an Adobe PDF file.

 

Suppliers should note that before submitting a response to the PQQ they must register their intent to do this with JANET(UK).

 

Each potential supplier must register on the JANET(UK) e-tendering opportunities portal at https://tenders.ja.net. Each potential supplier must register as a system user if they are a first time user of the JANET(UK) portal, which is a one-off activity. Once accepted by JANET(UK), each supplier will receive a username and password that should be used for all future accesses to the system. The only time that JANET(UK) will reject a supplier is if there is an attempt to have a duplicate registration for a supplier. Also, please note that this first time registration is not a registration for a particular contract, it is only the registration of the user on the JANET(UK) portal. When username and password are received, then a supplier must log in and then register their interest in a specific contract. It is recommended that a generic mailbox (such as sales@supplier) is set up, so that information from the system can be sent to more than one representative at the company.

 

The steps and timetable for this procurement are as follows:

Activity

Date

Notice of procurement in the EU journal

1st April 2011

Final date for clarifications

3rd May 2011

Close of registration to take part in the shortlisting

16:00 on 6th May 2011

Prequalification questionnaire returns by

12:00 noon, 9th May 2011

Complete review of responses, shortlist suppliers to enter the procurement process and issue OR and standard form of agreement

3rd June 2011

Return of  Operational Requirement responses

8th July 2011

Selection of preferred suppliers

5th August 2011

Contract placed with preferred suppliers

30th September 2011